Chapter 3 - Project Basis
Determining Roles
While Table 4 recommends general roles and responsibilities for team members, specific roles may shift as a result of budget limitations, unique building requirements, and facility staff expertise and availability. Finding the right balance between responsibilities for facility staff and the outside recommissioning provider can be tricky and requires a good understanding of the capabilities of the individuals involved.
A third-party recommissioning consultant27 is usually hired to lead the recommissioning effort. A building or facility manager, however, can manage the project and bring in a commissioning expert to assist with certain tasks. While it may be advantageous for the building staff to play a central role in a recommissioning project, having a recommissioning expert provide consultation is recommended, especially for large or complex projects and buildings with highly-integrated, sophisticated systems.
Four approaches for using a third-party recommissioning provider include:
CAUTION: While it may be tempting to have existing facility staff shoulder the majority of the recommissioning work, the key is to strike the right balance. If owners expect too much from staff, the process may stall or stop altogether. It may be helpful to think of the first recommissioning project as a capacity building opportunity for everyone, and to increasingly rely on in-house expertise with each successive project.
Good reasons to have a third-party recommissioning provider lead the recommissioning process include:
The following Table 5 shows the way roles were split for a large corporation with a highly experienced facility staff dedicated to the project. In this case, the energy manager developed an in-house recommissioning program to be used across all their facilities. The recommissioning provider served as a consultant for testing systems, analysing data, and training building staff throughout the process.28
| In-House Team | Third Parties (Recommissioning Provider and Subcontractors) |
| Design program | Act as resource |
| Conduct energy performance rating (e.g. benchmarking) | Review – assist as needed |
| Utility bill analysis | Review – assist as needed |
| Gather building documentation | Review |
| Create maintenance checklists (scheduled preventive maintenance) | Focus and train staff on operational improvements |
| Assist provider in data gathering | Conduct functional tests and data analysis (look at the root cause) |
| Implement easy to fix improvements | Assist with resolving design and complex implementation issues |
| Provide ongoing tracking and preventive maintenance | Provide ongoing support as needed |
| Obtain approval to implement improvements | Assist staff in developing the implementation proposal to upper management |
_______________
26 Natural Resources Canada's CanmetENERGY offers an Advanced Recommissioning Course targeted at recommissioning service providers and based on the RCx methodology described in this RCx Guide. Additional information is available on the Website.
27 I bid 26.
28 Haasl, Tudi, Robert Bahl, E.J. Hilts, and David Sellers. Appropriate Use of Third Parties in the Existing Building Commissioning Process – An In-house Approach to Retrocommissioning. World Energy Engineering Congress. (2004).
29 I bid 28.